Private villa, Doha
- Enquiry
- Quote and order
- Productionsince 22 Sep
- Delivery
- Payment
- Contract value
- €175,500
- 3 pieces
- Received / open
- €70,200
- €105,300 open · 40% received
- Next milestone
- 28 Nov
- 40% after quality control · €70,200
- Delivery date
- 9 Dec
- Arrives in Doha · loading 1 Dec
- Chase the finish sample approvalDue 18 Nov · LatifWaiting 6 daysLP
- Request the certificate of originDue 20 Nov · [Partner 2]In 2 daysP2
- Prepare the quality controlDue 26 Nov · LatifIn 8 daysLP
- Send the second invoiceDue 26 Nov · [Partner 3]In 8 daysP3
- Book flights for the install teamDue 30 Nov · [Partner 2]In 12 daysP2
Received €70,200Open €105,300
- Incoming: 40% after quality controlNot invoiced yet · quality control 26 Nov28 NovTo invoice€70,200
- Incoming: 20% after installationAfter installation, 14–20 Dec3 JanPlanned€35,100
- Incoming: 40% depositINV-2026-0396 OctPaid€70,200
- Foundry JPO-2026-061 · Brass arm blanks, chainDue 25 NovIn production€12,400
- Crystal supplier HPO-2026-062 · Pendalogues, bobechesDue 24 NovIn production€9,800
- Glass workshop EPO-2026-055 · Glass leaves, stairwellDue 25 NovGlass forming€8,600
- Electrical supplier KPO-2026-048 · LED drivers × 20Due 30 OctDelivered€820
- Gilding supplier LPO-2026-041 · Gold leaf, 40 booksDue 25 SepDelivered€1,900
People
3- Design Studio ACustomer · QatarApproval
- Fatima A.Designer · Design Studio AWaiting 6 days
- No contractor on fileContractor
Notes & activity
46Called Fatima A. about the finish sample
Order to Crystal supplier H, €9,800
Sample 2 declined by the designer, rework by 24 Nov
Order to Foundry J, €12,400
Truck booked for 1 Dec, 14 crates
Pieces
3| Piece | Model | Size | Finish | Lights | Qty | Now | Price |
|---|---|---|---|---|---|---|---|
| A · Atrium chandelier | LP Atrium, 3-tier | Ø 2,400 × 3,200 mm | Aged brass, gold leaf | 48 × E14 LED | 1 | Crystal dressing | €128,000 |
| B · Stairwell installation | LP Cascade | 9 m drop | Clear glass, brass | 60 LED points | 1 | Glass forming | €36,500 |
| C · Wall sconces | LP Sconce, 2-arm | 300 × 450 mm | Aged brass | 2 × E14 LED | 12 | Ready for crating | €11,000 |
Contract value€175,500
Piece A in detail
Weight
340 kg
Crystal
4,800 pendalogues
Ceiling load needed
500 kg
Hoist
Motorised, 6 m
Voltage
230 V, dimmable
Crates
6 of 14
Approvals
8| What | Piece | Sent to | Sent | Answer | Status |
|---|---|---|---|---|---|
| Concept drawings | All pieces | Fatima A.Design Studio A | 20 Aug | 24 Aug | Approved |
| Shop drawing, rev. C | A · Atrium chandelier | Fatima A.Design Studio A | 25 Sep | 2 Oct | Approved |
| Shop drawing, rev. B | B · Stairwell installation | Fatima A.Design Studio A | 25 Sep | 6 Oct | Approved |
| Sconce mock-up | C · Wall sconces | Sara B.Design Studio A | 22 Oct | 28 Oct | Approved |
| Finish sample 1, aged brass | A, C | Fatima A.Design Studio A | 5 Nov | 9 Nov | Approved |
| Finish sample, gold leaf | A · Atrium chandelier | Fatima A.Design Studio A | 12 Nov | – | Waiting 6 days |
| Sample 2, crystal cut | A · Atrium chandelier | Fatima A.Design Studio A | 10 Nov | 17 Nov | Declined |
| Installation method statement | All pieces | Site manager, Doha | By 1 Dec | – | Planned |
Orders to suppliers
| Supplier | What | Order | Ordered | Due | Status | Amount |
|---|---|---|---|---|---|---|
| Foundry J | Brass arm blanks, chain | PO-2026-061 | 15 Nov | 25 Nov | In production | €12,400 |
| Crystal supplier H | Pendalogues, bobeches | PO-2026-062 | 17 Nov | 24 Nov | In production | €9,800 |
| Glass workshop E | Glass leaves, stairwell | PO-2026-055 | 2 Nov | 25 Nov | Glass forming | €8,600 |
| Electrical supplier K | LED drivers × 20 | PO-2026-048 | 20 Oct | 30 Oct | Delivered | €820 |
| Gilding supplier L | Gold leaf, 40 books | PO-2026-041 | 18 Sep | 25 Sep | Delivered | €1,900 |
In the workshop
| Piece | Now | Next | Progress | Ready by |
|---|---|---|---|---|
| A · Atrium chandelier | Crystal dressing | Quality control | 65% | 26 Nov |
| B · Stairwell installation | Glass forming | Assembly | 40% | 28 Nov |
| C · Wall sconces × 12 | Ready for crating | Packing | 100% | Done |
Transport
Crates
14
Mode
Road, Istanbul → Doha
Loading
1 Dec
Arrival
About 9 Dec
Installation
14–20 Dec
Forwarder
Freight forwarder F
Export documents
| Document | Who | Status |
|---|---|---|
| Truck booking | Freight forwarder F | Booked |
| Cargo insurance | Freight forwarder F | Booked |
| Certificate of origin | [Partner 2] | Request by 20 Nov |
| Packing list | Latif | Draft |
| Commercial invoice | [Partner 3] | After quality control |
Installation team
| Who | Role | Flights |
|---|---|---|
| Mustafa D. | Lead installer | Book by 30 Nov |
| Kerem A. | Electrician | Book by 30 Nov |
| Can Y. | Installer | Book by 30 Nov |
| Burak S. | Installer | Book by 30 Nov |
| Site ready check | Design Studio A | Planned 10 Dec |
At a glance
- Contract value
- €175,500
- 3 pieces
- Received
- €70,200
- 40% of the contract
- Still to come
- €105,300
- 2 milestones
- Margin
- 28%
- After designer commission
Payment milestones
| Milestone | Invoice | Due | Status | Amount |
|---|---|---|---|---|
| 40% deposit | INV-2026-039 | 6 Oct | Paid | €70,200 |
| 40% after quality control | Not invoiced yet | 28 Nov | To invoice | €70,200 |
| 20% after installation | – | 3 Jan | Planned | €35,100 |
Contract value€175,500
Project costs
| Booked to | Status | Amount |
|---|---|---|
| Glass workshop E | Paid | €8,600 |
| Gilding L, Electrical K | Paid | €2,720 |
| Freight forwarder F | Due 28 Nov | €7,900 |
| Foundry J | Due 15 Dec | €12,400 |
| Crystal supplier H | Due 17 Dec | €9,800 |
| Workshop labour | Booked | €29,880 |
Cost so far€71,300
Documents
8| Document | Type | Added | By | Shared with |
|---|---|---|---|---|
| Contract, signed | 22 Sep | Latif | Design Studio A | |
| Quote Q-2026-031 | 15 Sep | Latif | Design Studio A | |
| Concept renderings | 4 images | 20 Aug | Latif | Design Studio A |
| Shop drawings A and B, rev. C | 6 Oct | [Partner 2] | Design Studio A | |
| Invoice INV-2026-039, deposit | 22 Sep | [Partner 3] | Design Studio A | |
| Finish sample photos | 6 images | 12 Nov | Latif | Design Studio A |
| Freight booking confirmation | 14 Nov | [Partner 3] | Internal | |
| Packing list, draft | Excel | 17 Nov | Latif | Internal |
History
46| When | Who | What | Area |
|---|---|---|---|
| 18 Nov, 10:20 | Latif | Called Fatima A. about the finish sample | Call |
| 17 Nov, 16:30 | [Partner 2] | Order to Crystal supplier H, €9,800 | Production |
| 17 Nov, 10:02 | Latif | Sample 2 declined by the designer, rework by 24 Nov | Approvals |
| 15 Nov, 12:20 | [Partner 2] | Order to Foundry J, €12,400 | Production |
| 14 Nov, 17:55 | [Partner 3] | Truck booked for 1 Dec, 14 crates | Shipping |
| 12 Nov, 15:10 | Latif | Finish sample, gold leaf, sent to Design Studio A | Approvals |
| 9 Nov, 11:45 | Latif | Finish sample 1 approved | Approvals |
| 2 Nov, 09:30 | [Partner 2] | Order to Glass workshop E, €8,600 | Production |
1–8 of 46